Construction Status Report

 

CITYWIDE WATER SERVICE LINE REPLACEMENT PROJECT PHASE 1
(Updated May 2017)

Limits:
Residential areas bounded by Orangewood Ave, Magnolia St, Katella Ave, and Brookhurst St.

Awarded to Stephen Doreck in July 2015.
Start Date: October 2015
Status: 99% complete
Completion Date: May 2017

PRV & MWD INTERCONNECT FACILITIES REHABILITATION PROJECT
(Updated May 2017)

Limits:
Two (2) PRV's and three (3) OC Interconnects throughout the City

Awarded to Cora Constructors in November 2016
Start Date: January 2017
Status: 60% complete
Completion Date: July 2017

SEWER IMPROVEMENTS PROJECT
(Updated May 2017)

Limits:
Imperial Avenue (Magnolia St to Vaughn Ln)
Nutwood Street (Molama Cir to Garden Grove Blvd)

Awarded to Mamco, Inc. in June 2016
Start Date: August 2016
Status: 99% complete
Completion Date: May 2017